Heat Seal Coatings: A Selection Checklist

How to brief a supplier about lidding, paper structures, seal targets and end-use requirements.

Technical guide About 6 min read Practical FAQs & checklists
Application note

A heat seal coating must work with the actual sealing surface and the intended packing process.

In this guide

Define a coating brief, understand the difference between seal initiation and seal strength, plan process trials, and diagnose peel, leak and blocking issues before selecting a heat seal coating.

1. What does a heat seal coating do?

A heat seal coating is applied to a substrate so it can form a bond to another compatible surface when sealing equipment supplies the required combination of temperature, pressure and dwell time. The final performance depends on both surfaces, coating and dry coat weight, drying/curing, equipment geometry and storage conditions.

Common packaging discussions include foil or paper-based lidding, coated paper, and other selected structures. The correct coating is not defined by the lid material alone. A foil lid sealed to PP, PE, PET, PS or a coated board, for example, may require entirely different qualification routes.

2. First define the complete package

  1. Lidding or top web: Is it aluminium foil, paper, PET, a laminate or another substrate? Provide gauge, grade, primers, coatings and print history.
  2. Receiving surface: Is the tray/cup/flange made of PP, PE, PS, PET, coated paper or a specified barrier structure? State the surface that actually touches the heat seal coating.
  3. Required opening behaviour: Easy peel, controlled peel, strong/fibre-tear or permanent seal? Describe the consumer’s opening experience.
  4. Equipment: State jaw design, nominal/verified temperature, pressure, dwell time, line speed, sealing area and tooling condition.
  5. End use: Ambient, chilled, frozen, hot-filled, retort or other thermal processing? Do not assume a coating meets these conditions without testing.
  6. Regulated use: Identify food, medicine or other contact-sensitive applications and target markets early. Obtain suitable supporting regulatory evidence for the exact application.

Example — foil lidding onto a rigid tray

A supplier must know the foil/primer structure, the receiving tray polymer or coating, required peel force, seal width, actual machine conditions, storage temperature and any sterilisation/heat exposure. “Foil-to-tray, 180°C” is not a complete specification; measured temperature at the seal interface may differ from a set-point.

3. The performance terms everyone should understand

ParameterWhat it tells youWhat to report
Seal initiation temperature (SIT)Temperature region where useful seal strength starts to develop under defined conditionsTest method, dwell, pressure, coating/structure and acceptance threshold
Seal strengthForce needed to separate a defined seal specimenSpecimen width, conditioning, test angle, peak/average and failure mode
Hot tackStrength of a freshly formed seal while still hotTime after sealing, equipment and load conditions
Peel behaviourWhether a seal opens smoothly or tears fibre/film or fails at an interfaceDesired peel type, force window and visual failure description
Seal windowRange of temperature/time/pressure where the required result is obtainedMinimum and maximum validated process conditions
Coat weight and uniformityCoverage and mass of dried coating affecting bond, costs and handlingSpecified dry coat weight and its control method
Blocking / storage resistanceTendency of coated stock to stick during rewind, stacking or warehousingRelevant time, pressure, temperature and humidity exposures
Package integrityWhether the assembled pack maintains its intended barrier/closureAgreed leak, burst, dye, vacuum or other application-specific test

A single reported seal strength number is not comparable unless test set-up, specimen and failure mode are also comparable. Avoid stating a universal sealing temperature or strength without a validated grade-specific method.

4. Structured coating qualification plan

Stage A — Laboratory screening

  • Confirm coating/substrate and receiving-surface compatibility, approved preparation and application conditions.
  • Prepare representative coated samples at controlled dry coat weight, drying and conditioning.
  • Use a planned temperature/dwell/pressure matrix to create a seal curve, not one preferred set-point.
  • Measure seal strength and inspect seal modes; consider hot tack for fast fill/seal lines.

Stage B — Pilot machine trial

  • Test at normal operating speed with representative tooling and material batches.
  • Observe wrinkles, puckering, coating transfer, jaw sticking, uneven seals, peel quality, edge leakage and contamination.
  • Check the difference between instrument set-point and effective interface conditions if results vary.

Stage C — Final-pack validation

  • Condition packs as required for the real distribution and storage environment.
  • Test package integrity and target opening behaviour after storage, thermal exposure and handling where relevant.
  • Record acceptance criteria, samples, failures, corrective actions and approved operating window.

Standards to discuss with your test laboratory

ASTM F88/F88M addresses seal-strength measurement of flexible barrier materials; ASTM F1921 addresses instrumented hot-tack testing for applicable flexible webs; ASTM F2029 covers laboratory heat-seal practices for flexible barrier materials. The correct version and suitability of each method should be confirmed for your package.

5. Troubleshooting heat seal failures

SymptomInvestigatePotential next test
Low or inconsistent seal strengthTemperature, time, pressure, poor coat coverage, wrong receiving surfaceControlled seal curve and coat-weight audit
Seal tears the lid or trayPeel target, coating bond, substrate toughness, test techniqueFailure-mode assessment and target peel window
Seal opens too easilyCoating/receiving-surface mismatch, insufficient pressure/dwell or contaminationRepeat with verified clean surfaces and settings
Blocking in reelsInsufficient drying, residual volatiles, rewind temperature/tension, storageConditioning and blocking comparison tests
Seal leaks despite good pull forceWrinkles, channels, flange defects, product contamination or local coating gapsPackage-integrity test plus visual seal mapping
Sealing jaw depositsCoating transfer, wrong process window, release properties and cleaningTool temperature verification and deposition inspection

6. What your supplier quotation or sample request should contain

7. Frequently asked questions

Is a lower seal initiation temperature always preferable?

Not necessarily. The required seal window must also provide bond reliability, hot tack, blocked-roll resistance and correct opening behaviour without damaging the package.

Can one coating seal to PP, PE and PET?

Only when the specific coating is qualified for each actual receiving surface and package construction. Polymer labels alone are not a sufficient basis for approval.

Why is my lab seal stronger than a production seal?

Laboratory jaws, temperature measurement, dwell, pressure distribution, surface cleanliness and sample preparation can differ from the commercial line. Compare measured conditions and package geometry.

Is seal strength equal to leak tightness?

No. A strong local pull test does not demonstrate that the entire perimeter seal is continuous. Evaluate package integrity with an appropriate method.

How does hot tack differ from cooled seal strength?

Hot tack assesses the seal very soon after forming, while it is still hot; conventional seal-strength tests often measure conditioned/cooled seals. Both may matter for fast filling machinery.

Can a website article establish food or pharma compliance?

No. Regulated use needs product-specific composition/documentation, packaging design assessment, market-specific review and validation as applicable.

Technical references

ASTM F88/F88M — Seal strength · ASTM F1921 — Hot tack · ASTM F2029 — Heat-seal practice overview

This is general technical education, not a BC Petrochem grade specification, operating instruction or confirmation of regulated-use suitability. Always obtain the relevant current TDS/SDS, confirm applicable requirements and approve the finished structure through representative tests.
Discuss Your ApplicationExplore ARO Products← All technical insights
LET'S COLLABORATE

Have a printing or packaging challenge?

Share your substrate, print process and end-use requirements with BC Petrochem.

Discuss Your Requirement